High Court halts A5 dual carriageway project


THE future of the long-delayed A5 dual carriageway project has been thrown into doubt after a High Court judge ruled against the £1.7bn scheme this morning in Belfast. Justice Michael McAlinden said the Department for Infrastructure failed to properly assess the road’s impact on climate change targets and cited “inadequate information for lawful decision making.”
THE future of the long-delayed A5 dual carriageway project has been thrown into doubt after a High Court judge ruled against the £1.7bn scheme this morning in Belfast.
Justice Michael McAlinden said the Department for Infrastructure failed to properly assess the road’s impact on climate change targets and cited “inadequate information for lawful decision making.”
The A5 project - first proposed in 2007 - aimed to upgrade the 58-mile route connecting Londonderry and Dublin via key towns like Omagh and Strabane.
It has faced years of legal challenges and delays, despite strong backing from campaigners and funding commitments from both Stormont and the Irish government.
More than 50 lives have been lost on the road since 2006, fuelling calls for urgent safety improvements.
But opposition from landowners and environmental groups has persisted, with the latest ruling potentially sending planners back to the drawing board.
The Department for Infrastructure has yet to confirm its next steps.